The Georgian Railway has announced an international tender for the construction of a line that will connect the deep-water port of Anaklia with the national railway network. The project cost is estimated at approximately $205 million. The new infrastructure is to be ready by 2029, the deadline authorities are targeting for the launch of the port.
According to the company, the project provides for the construction of a 17.7 km electrified railway. The branch will start from the existing main line in the area of the village of Khamiskuri and will be laid directly to the port. In addition, a new railway station will be built in Anaklia, and the infrastructure of the Hobi station will be reconstructed.
The project is being implemented with financial support from the World Bank. The work period will be 30 months after the contract is signed.
The construction of the Anaklia deep-water port, which the Georgian authorities call the "project of the century," was postponed for almost ten years. In 2020, the government terminated the investment agreement with a Georgian-American consortium, after which the implementation of the project effectively stopped.
The authorities returned to the idea against the backdrop of the growing importance of the Middle Corridor. In July 2026, the government presented an updated port development model: the "landlord" model. Unlike the original plan with a single private investor, the state now takes on the construction of the basic infrastructure, while individual terminals are planned to be transferred to international operators on long-term lease.
To implement the first phase of the project, the government plans to attract about $200 million in international financing. According to estimates from the Ministry of Economy, another $350–400 million could be invested by private companies in equipment and terminal development.
In addition to the railway branch, the state is funding the construction of a road to the port and other infrastructure. According to budget documents, total expenditures on the development of Anaklia until 2030 are already planned at 572 million lari.
The first phase of the port itself is planned to be completed in 2029. After reaching design capacity, it will be able to handle up to 600 thousand containers per year.